When the Defense Contract Audit Agency questions costs—on an incurred-cost submission, a claim, or a termination proposal—the contractor's exposure is the gap between what it billed and what it can support. That gap is an accounting problem with a well-defined structure. Costs charged to a government contract have to clear three tests, and most questioned-cost disputes are a fight over one of them.
1. Allowable
FAR Part 31 and the contract terms define what the government will pay for. Some costs are expressly unallowable (certain interest, entertainment, lobbying, and the like); others are allowable only within limits or with specific support. The discipline is to identify and segregate expressly unallowable costs in the accounting system before they are ever billed—because an unallowable cost that gets included, and then penalized, costs more than the cost itself.
2. Allocable
A cost is allocable if it was incurred for, and can be assigned to, the contract in a reasonable proportion to the benefit received. This is where indirect cost pools and allocation bases do their work: overhead and G&A have to be pooled consistently and spread on a base that matches the contractor's disclosed practices. Allocations that shift cost toward government work, or that don't match the books, are the classic audit finding.
3. Reasonable
A cost is reasonable if it does not exceed what a prudent person would incur in a competitive business. Reasonableness is the softest of the three tests and the one most often asserted rather than measured. The answer comes from comparables, documented decision-making, and the contractor's own history—not from a conclusion.
Where the disputes actually live
In practice, questioned costs cluster in a few places: indirect rates that don't reconcile to the general ledger; executive compensation above the supportable range; costs that should have been segregated as unallowable but weren't; and inter-company or related-party charges without arm's-length support. Each is an accounting question with a documentary answer.
The job in a dispute
Responding to questioned costs is reconstruction and reconciliation: tying each challenged cost back to the ledger, the timecard, the invoice, and the disclosed accounting practice; showing where the auditor's adjustment rests on an assumption the records don't support; and quantifying the defensible number. Whether a particular cost is legally allowable can be a question for counsel, but the foundation is always the same—what the contractor's own system can prove.